Public paper · October 10, 2026 · Energy desk

FERC Notice: Eastern Shore Natural Gas Seeks Approval for $75.1 Million Delmar Regional Enhancement Project in Pennsylvania, Delaware and Maryland; Intervention Deadline October 26

The Federal Energy Regulatory Commission (FERC) noticed Eastern Shore Natural Gas Company's application (Docket CP26-585-000) for pipeline loops and replacements in Chester County, Pa., New Castle, Kent and Sussex counties, Del., and Cecil County, Md. Motions to intervene are due by 5 p.m. Eastern on October 26, 2026.

Crew welding a section of pipeline (historical photo, not the Delmar project). Photo: US Army via Wikimedia Commons (Public domain).
Crew welding a section of pipeline (historical photo, not the Delmar project). Photo: US Army via Wikimedia Commons (Public domain).

Download PDF

noticenearby.com/papers/ferc-eastern-shore-delmar-regional-enhancement-project-cp26-585.pdf

The Federal Energy Regulatory Commission (FERC) published a Notice of Application and Establishing Intervention Deadline in the Federal Register on October 8, 2026 (FR Doc. 2026-20659, 91 FR 64368) for Eastern Shore Natural Gas Company's Delmar Regional Enhancement Project, Docket No. CP26-585-000.

Eastern Shore, of Dover, Delaware, filed its application on September 24, 2026 under sections 7(b) and 7(c) of the Natural Gas Act.

What is proposed

  1. Build the approximately 2.55-mile, 24-inch Parkesburg-Daleville Loop in Chester County, Pennsylvania.
  2. Replace two segments of the 6-inch Tidewater Line, about 1.6 miles in total, with 16-inch pipe in New Castle County, Delaware.
  3. Build the 5.05-mile, 16-inch Harrington Loop in Kent County, Delaware.
  4. Build the 1.85-mile, 24-inch Barksdale Loop in Cecil County, Maryland.
  5. Abandon in place or remove about two miles of the Tidewater Line in New Castle County.
  6. Remove the existing North Bridgeville Meter and Regulator Station and build a new one in Sussex County, Delaware.
  7. Build associated aboveground valve facilities.

Eastern Shore says the project is fully subscribed and would provide 15,800 dekatherms per day of new firm transportation service to Easton Utilities Commission and Chesapeake Utilities Corporation–Delaware Division. It estimates the cost at $75,130,000.

How to take part

  • Intervention deadline: 5:00 p.m. Eastern, October 26, 2026. FERC says a motion to intervene should state your position and interest, such as landowner, ratepayer, resident of an affected community or recreationist, and that you do not need property directly affected by the project to intervene.
  • Documents: in FERC eLibrary under docket CP26-585. FERC Online Support: (202) 502-6652 or toll-free 1-866-208-3676.
  • Company contact: Katelyn Richardson, Regulatory Analyst IV, Eastern Shore Natural Gas Company, (302) 242-5480.

Source

  • Federal Register, FR Doc. 2026-20659, FERC, "Eastern Shore Natural Gas Company; Notice of Application and Establishing Intervention Deadline," October 8, 2026.

Notes and sources

  1. Author: Ryan Standley / Record of Sale, LLC / Notice Nearby.
  2. Discussed on @NoticeNearYou: (pending — fill xPostUrl after live post).
  3. Not legal advice. Not a newspaper. Not Legal Publication. Record of Sale, LLC (Oregon).

Energy desk · Notice Nearby public papers shelf. @NoticeNearYou post pending.

Not legal advice. Not a newspaper. Not Legal Publication. Record of Sale, LLC (Oregon).