FERC Says Dominion Energy's Stevens Creek Hydroelectric Relicensing on the Savannah River Is Ready for Environmental Review; Comments Due December 6

The Federal Energy Regulatory Commission says Dominion Energy South Carolina's application for a new license for the 17.28-megawatt Stevens Creek Hydroelectric Project, on the Savannah River between South Carolina and Georgia, is ready for environmental analysis. Comments and agency conditions are due December 6, 2026.

U.S. Army Corps of Engineers crew at New Savannah Bluff Lock and Dam, Augusta, Georgia, downstream on the Savannah River (illustrative, not Stevens Creek dam). Photo: U.S. Army Corps of Engineers Savannah District via Wikimedia Commons (Public domain).
U.S. Army Corps of Engineers crew at New Savannah Bluff Lock and Dam, Augusta, Georgia, downstream on the Savannah River (illustrative, not Stevens Creek dam). Photo: U.S. Army Corps of Engineers Savannah District via Wikimedia Commons (Public domain).

Download PDF

noticenearby.com/papers/ferc-stevens-creek-hydro-relicense-savannah-river-comments-dec-6.pdf

The Federal Energy Regulatory Commission (FERC) has issued a notice that the relicensing application for the Stevens Creek Hydroelectric Project (Project No. P-2535-129) is ready for environmental analysis. FERC is asking for comments, recommendations, terms and conditions, and prescriptions. The notice is on Federal Register public inspection as FR Doc. 2026-20881.

The project

  • Applicant: Dominion Energy South Carolina, Inc.
  • Application: new major license, filed October 27, 2023
  • Location: where Stevens Creek meets the Savannah River, in Edgefield and McCormick counties, South Carolina, and Columbia County, Georgia. About 104 acres are federal land run by the U.S. Forest Service.
  • Facilities: a 2,400-acre reservoir holding 23,699 acre-feet, a dam with flashboard sections, an inoperable navigation lock, and a three-story brick powerhouse with eight generating units totaling 17.28 megawatts
  • Recreation: the Stevens Creek recreation site and the Fury's Ferry boat ramp, among others

Deadlines

  • Comments, recommendations, terms and conditions, and prescriptions: 5 p.m. Eastern, December 6, 2026
  • Reply comments: 5 p.m. Eastern, January 20, 2027

How to take part

File through FERC eComment (no registration needed, up to 10,000 characters) or eFiling at ferc.gov, and cite P-2535-129. FERC contact: Jeanne Edwards, (202) 502-6181. Office of Public Participation: (202) 502-6595.

Why it matters locally

A new license sets the rules for decades of reservoir levels, flows, fish passage and boat ramps around Augusta and North Augusta. This comment window is when residents and agencies can ask for license conditions.

Source

  • Federal Register public inspection, FR Doc. 2026-20881, FERC, "Dominion Energy South Carolina, Inc.; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions" (Project No. 2535-129).

Notes and sources

  1. Image: U.S. Army Corps of Engineers crew at New Savannah Bluff Lock and Dam, Augusta, Georgia, downstream on the Savannah River (illustrative, not Stevens Creek dam). Photo: U.S. Army Corps of Engineers Savannah District via Wikimedia Commons (Public domain).
  2. Author: Ryan Standley / Record of Sale, LLC / Notice Nearby.
  3. Discussed on @NoticeNearYou: (pending — fill xPostUrl after live post).
  4. Not legal advice. Not a newspaper. Not Legal Publication. Record of Sale, LLC (Oregon).

Energy desk · Notice Nearby public papers shelf. @NoticeNearYou post pending.

Not legal advice. Not a newspaper. Not Legal Publication. Record of Sale, LLC (Oregon).